All Collections
Collect data on site
Perform field surveys
Setup the steps for adding a located task to a plan
Setup the steps for adding a located task to a plan

Set the settings that suit you in order to optimize your field surveys

Djouher Mezahem avatar
Written by Djouher Mezahem
Updated over a week ago

iOS Version

This tutorial shows you how to improve the steps for adding a located task to a plan/drawing.

  1. Go to the project in which you intend to create your new task.

  2. Click on Plans in the navigation bar.

  3. Select a plan

  4. Click on the Settings Button

  5. By selecting the steps of the path you wish to modify, you can now :

    • Define an assignee for each task that will be added to the plan.

    • Add a due date to each task that will be added to the plan.

    • Choose to activate or deactivate the camera automatically after placing the task.

    • Display the task after you complete all the steps.


Android Version

  1. Go to the project in which you intend to create your new task, then Click on Plans in the navigation bar.

  2. Select a plan

  3. Click on the Settings Button at the bottom right of your screen.

  4. By selecting the steps of the path you wish to modify, you can now :

    • Define an assignee for each task that will be added to the plan.

    • Add a due date to each task that will be added to the plan.

    • Choose to activate or deactivate the camera automatically after placing the task.

    • Display the task after you complete all the steps.

Did this answer your question?