  1. Go to the task you would like to set a date and click on the down arrow icon.

  2. Tap on the date you want to edit. In Bulldozair you can add several different dates:

    • A start date

    • An observation date

    • A done date => date on which the Task was completed

    • A due date

  3. Select the date you need then press Save.


Android Version

To add/change a date of your task from the Android app, you must:

  1. Go to the task then click on the calendar icon at the bottom of your screen.

  2. Select the type of date you would like to add and click on Save


iOS Version

  1. Go to the Task you want to edit.

  2. If the type of the date you wish to enter is a performing date or an observation date, scroll through all the dates by pressing the button below. Otherwise go directly to step 3.

  3. Press the date you want to edit.